Blast Furnace Reline Nears End

As a major contractor Allfab has been involved in the planning and implementation of this project since 2006 and has played a pivotal role in the completion of the Gas Cleaning and Hot Blast System’s for the No.5 Blast Furnace Reline. 

Successfully completing the Downcomer, Dustcatcher,  and Scrubber installations to help Bluescope meet new levels of environmental compliance.

In the process Allfab met the challenge of changing the Diffuser which was not part of the original scope and involved the heaviest crane lifts of the project. 

Additionally Allfab renewed and refurbished key components for the Hot Blast and Cold Blast Systems to enable the furnace to operate at maximum efficiency. 

This  involved replacing the Hot Blast Valves, Associated Pipework and Mains.     

Blast Furnace Reline Nears End

Latest News.

Expression of Interest in Employment

Interested in Future Employment? Then this may be for you. We have upcoming opportunities, so register your interest.

Bluescope Safety Award

BOS Flare Stack Crews recognised for Outstanding Safety Performance.

2010 Employee of Year

The ‘2010 Employee of the Year’ was again a very hotly contested award. And the winner is....

 

Projects.

BSL Boiler Installation

BSL Boiler Installation

Installation No.11 and 12 High Pressure Client Supplied and Manufacture “Package Boiler” Units.

Bluescope Transfer Pit Upgrade

Bluescope Transfer Pit Upgrade

The project totalling 20,000 Man Hours was carried out with zero harm and ahead of schedule.

Bluescope Flare Stack Replacement

Bluescope Flare Stack Replacement

Allfab were engaged to demolish and Install of No1, 2 and 3 Flare Stacks Bluescope’s Port Kembla BOS Facility.