Map of allfab office location

Company Contacts.

HEAD OFFICE
Lot 9 Shellharbour Road
Port Kembla
NSW 2505

Phone: +61 2 4274 6222
Fax: +61 2 4276 1038 

Email us

Bluescope Transfer Pit Upgrade

Allfab’s scope of work was to replace No.1  No.2 and No.3 Transfer Pit (Slag Car) Foundations and Rails in an open book contract.  

The working was made increasing challenging as it was to be completed whilst working next to operating furnaces with production interactions and additionally the scope for the demolition of existing foundations were unknown.  

Each pit was programmed to be completed in 22 days, Allfab’s Management engineered solutions to allow the work to be completed in 18 days, a 19% reduction in downtime.

 The modular assembly templates, skid designs and pre-assembled bearer plates used not only enable easier installation it also realised cost savings with a  24% reduction in estimate.

As Prime Contractor Allfab was solely responsible for the control, programming and safety planning of the major civil sub-contractor.  

The project totalling 20,000 Man Hours was carried out with zero harm, no lost time, medical treated or first aid injuries including our managed civil sub-contractors.  

More information

Bluescope Transfer Pit Upgrade

allfab transfer pits.pdf
Pre-assembly of Modulars
 

Projects.

BSL Boiler Installation

BSL Boiler Installation

Installation No.11 and 12 High Pressure Client Supplied and Manufacture “Package Boiler” Units.

Bluescope Transfer Pit Upgrade

Bluescope Transfer Pit Upgrade

The project totalling 20,000 Man Hours was carried out with zero harm and ahead of schedule.

Bluescope Flare Stack Replacement

Bluescope Flare Stack Replacement

Allfab were engaged to demolish and Install of No1, 2 and 3 Flare Stacks Bluescope’s Port Kembla BOS Facility.